Building Progress

Want to stay up to date with the progress of our building expansion? You’ve come to the right place! With each phase, we will keep you informed of what’s going on and how it will affect our ministries.

Questions?

Contact John Hilliard at 717-755-0089 x 109

August 18, 2017:
Construction Continues!

A lot of progress under the roof was made this week.  And you will see some of those changes as you enter the church building this coming Sunday.  Thank you again for your patience and tolerance during this exciting project, especially navigating the building and parking lots on Sunday. 

Changes to the North side entrance to the church:  

  1. The North Side Handicap Parking will remain in front of Door 5 for the next few weeks.  Door 5 leads directly into Kid:Life and is the shortest route to the Main Lobby from the north handicap parking.  A new sidewalk was installed between Door 5 to Door 4, which will be the shortest route to the main hallway from Kid:Life to Common Grounds.
  2. To facilitate entering Doors 2 and 3 from the North Parking Lot, we created a new path from the North parking lot to the motor cycle lot and directly into Door 2.  Or, at that point, you may turn to the right along the existing sidewalk to Door 3.
  3. The retaining wall for the entrance flower beds were installed. And the roof extension was framed this week. 

  4. The drainage collection tanks and the front curb having been completed, the parking lot in front of the office additions was filled in, leveled, ready for the first coat of paving by the end of the month.

 

Changes to the Hallway between Common Grounds and the Main Lobby 

This hallway will be expanded in width from the kitchen into the main lobby.  Demolition started this week.  The old carpet was removed and the concrete was brushed clean.  And the ceiling was removed so you will see into the overhead.  But all is safe and the hallway is open for traffic on Sunday.

Main Office & Common Grounds Lobby Addition: 

The main office addition is water tight, and this week drywall was installed and taped in all the rooms.

 

The Common Grounds entrance framing and mechanical/electrical rough ins continued this week.

Student::life Renovations:    

To create space for more Middle School ministry we are expanding the Garage. The  new acoustical ceiling was sprayed this week.

The student::life entrance to the garage and restrooms will be blocked off until the renovations are complete.  

The exterior wall, insulation and blueskin waterproof was substantially complete.  Installation began for the new electrical conduits and ventilation ducting in the overhead and the last section of slab was poured.  This new space will contain the new prayer room, small group rooms, and large-group gathering space, and new women’s restroom.

kid::life Addition: 

There was no new work done on the Kid:Life structure.  The wall framing, insulation, waterproofing, and roof decking were rescheduled for next week.   

Last week room 350 (the Sunday breakout room for 3rd and 4th graders and across from studio 34) started renovation and expansion into the existing corridor to create more space for ministry. The new wall and new door framing was installed this week and the wall between the hallway and room 350 was removed.

Main Lobby Addition:   

Rains this week delayed the completion of the underground plumbing for the new café kitchen which is schedule now for completion next week.  The majority of the area was filled in and leveled in preparation of stone and slab preparation next week.

 

August 11, 2017:
Staying on Track, Rain or Shine

The Church Building Committee had their biweekly meeting with the prime contractor, Wohlsen on Thursday, Aug 10.  We have had some significant rains the last 2 weeks that have caused some exterior delays, but with the great contractor company/team we have, we are still seeing progress all over the building. Wohlsen is working on a revised project plan to keep us on track for an on-time completion. Thank you for your patience and tolerance during this exciting project, especially when navigating the building and parking lots on Sunday. 

Changes in Entrances on the North Side of the Church: 
Modifications to the patio/parking lot interface in front of Door 3 will require the patio to be fenced off; therefore, two new changes to entering the north side of the church will be implemented starting Sunday, August 13:   

  1.  The north side handicap parking will be moved from in front of doors 2 and 3 to in front of door 5, the entrance to kid::life. 
  2. To facilitate entering doors 2 and 3 from the north parking lot, we have created a new path from the north parking lot to the motorcycle lot and directly into door 2. Or, at that point, you may turn to the right along the existing sidewalk and enter at door 3.

Main Office & Common Grounds Lobby Addition: 

Progress continued for the interior mechanical, electrical, and plumbing rough-ins, as well as drywall and insulation installation.   

For the exterior, this week the concrete interface between the sidewalk and the parking lot was poured. Expect the sidewalk to be poured next week and the insulation and waterproofing to be completed.

student::life Renovations:    

To create space for more Middle School ministry, we are expanding the Garage. Demolition and some wall framing continued this week. The platform and other framing renovations were completed, and the room taped off in preparation for the new acoustical ceiling spray.

 

The student::life entrance to the garage and restrooms will be blocked off until the renovations are complete.  

Outside the exterior wall framing for the student::life addition was completed and the insulation and exterior drywall was installed.  Once in-ground plumbing was completed, the second half of the concrete floor slab was poured. This new space will contain the new prayer room, small group rooms, large-group gathering space, and new women’s restroom.

kid::life Addition:    

The structural steel framing was completed this week and some roof decking installed. The wall framing and insulation will be started next week.

Last week, room 350 (the Sunday breakout room for 3rd and 4th graders across from studio 34) started renovation and expansion into the existing corridor to create more space for ministry. The contractor continued the demolition of walls and ceilings in this area.

Main Lobby Addition:

The final section of cinder block foundation was laid this week between the kid:life and student:life additions. The last underground plumbing for the new kitchen was laid out and should be finished next week.

 

 

August 4, 2017:

The projects are still on schedule. We have had a few delays with the rain, but with the great contractor company/team we have, we are seeing great progress all over the building. Thank you for your patience and tolerance during this exciting project, especially navigating the building and parking lots on Sunday.

Main Office & Common Grounds Lobby Addition: 

Progress continued for the interior mechanical, electrical, and plumbing rough-ins, as well as drywall and insulation installation.

The exterior wall framing and sheathing continued to be installed on the new tower and Common Ground Lobby walls. The purple material you see is the sheathing. Water shield material was installed on the curved roofs at the new entrance.  

kid::life Addition: 

More structural steel was erected and detailing began on the new hallway, bathrooms, Basecamp, and large-group room. The second section of concrete was poured for these rooms as well.  

This week, room 300 (the second room used for studio 34 on Sunday) went under renovation to create more space for ministry. The contractor continued the demolition of walls and ceilings in this area.


Main Lobby Addition:  

Underground plumbing for the deep storm water lines installation continues. This week, even with the rain, the crew was able to pour more concrete for the footings and piers. 

 

student::life Renovations:   

To create space for more Middle School ministry we are expanding the Garage. Demolition and some wall framing continued this week. The new platform is starting to take shape.

The student::life entrance will be blocked off for a while until the demolition and new wall framing is complete. This week the contractors sawcut and removed part of the existing concrete slab to work on underground plumbing inside the building. 

Outside, more structural steel was installed and concrete floor slabs were poured for the new prayer room, small group rooms, and large-group gathering space.

   

 

July 28, 2017:
kid::life Expansion Begins!

This week we can see major visible progress in the kid::life and student::life renovations!

kid::life Expansion:

The structural steel and concrete foundations began being installed this week. The steel you see will eventually be the new Basecamp room and new bathrooms.    

Main Office & Common Grounds Addition:

Interior metal framing and drywall installation continued in the new office area. You will see more exterior installation added to the
Common Grounds entrance and lobby.

Main Lobby:

Installation continues for the foundations, piers, and concrete block foundation wall. 

student::life Renovations:

There have been major changes this week in student::life. The hallway bathroom demolition was begun, as well as walls, ceilings, and flooring. On Sunday, the entrance to the Hub will be blocked off. Please enter the student::life area through the student::life door by outside door 2. We will a lot of directional signs and welcome team members to help students navigate the hallway. Thank you for your patience during these improvements.

July 21, 2017:
Office Renovations Almost Complete!

This Sunday there are two main things to be aware of as you navigate the building. There is a new sidewalk installed for door #1. It’s extremely safe even though it’s temporary during this construction. Also, the bathrooms in the student::life wing are closed because they will be removed in the renovation. The door on the left side of the Life Center by student::life will be closed for the renovation of the student::life area. Once the renovation is complete it will be reopened.

Renovated Staff Offices: The staff office renovation is now partially complete. This week some of our staff moved into the renovated space with a new floorplan, fresh paint, carpet, lights, and ceilings.


The cut-through hallway from Common Grounds to kid::life is almost completed but is not open yet. Thank you for your patience, as it will be open very soon.

New Office Addition Exterior: Placing of the stone veneer on the outside walls was begun.

Window frames were installed and the framing began for the doorways and hallways.



New duct mains were installed in the office area as well.

student::life Area Addition: The structural steel installation continued and a concrete foundation was poured in the new area that will have meeting rooms for small groups and communities.


You will see white pipes sticking out of the ground. This piping is part of our underground storm water, roof drain, and sanitary plumbing.


Inside the student::life wing the renovations for the Garage continue with electrical and A/V demolition.

kid::life Renovations: Outside, underground plumbing and drain line installation began, as well as the foundation for the new classrooms. Inside, new doors were cut into rooms 322 and 323 on either side of the new hallway for the new classrooms and Basecamp.

Main Lobby Expansion: Foundation work continued with the installation of the foundational support for the newly expanded lobby steel. You will see concrete blocks being laid for the foundation.

The existing sidewalk outside of door #1 was removed to allow completion of footings and underground plumbing. A new temporary sidewalk was installed. It’s extremely safe and handicap accessible.

 

 

 

July 13, 2017:
Next Phase Begun in student::life Wing

New Office Expansion: To the right of the Common Grounds entrance and tower is the new office expansion. This week the underlayment for the roof was installed, as well as the exterior wall vapor barrier and wall sheeting. Inside, the electrical conduit and vent ducts along the ceiling were completed.


The old driveway in front of the office expansion and Common Grounds entrance was removed this week to accommodate the relocation of several storm drains. The drains and piping were relocated and backfilled as planned.


New Main Hallway and Office Renovations: The new main corridor from Common Grounds to kid::life and the adjacent renovated office spaces are in the final stages of completion. We expect the main corridor and adjacent renovated office spaces to be turned over to the church next week.

Hangar Renovations and Hallway Shut Down in student::life Wing: The next phase of renovations will take place in the student::life Garage and the corridor between the Hub/Garage and the Life Center (beginning just past the double doors leading into the Hub).

Note: Beginning Sunday, July 16, the Garage will be closed off. Beginning Monday, July 17, for the next several weeks, the hallway between the Hub/Garage and Life Center (beginning just past the double doors leading into the Hub) will be closed off.

Here is the blueprint of the new student::life expansion and surrounding area! We have plans for 6 breakout rooms that student::life and many other ministries can use in their learning communities. The Garage is being redesigned with a new floor plan, bathrooms are being moved, and we are creating a new lobby area for student check-in.


Foundations for the student::life, kid::life, and Main Lobby Expansions: Final underground plumbing for new restrooms on both wing expansions was completed this week and the area backfilled. Stone was laid in the new student::life wing expansion area with the slab in that area scheduled to be poured late this week or early next week. The most noticeable change was the structural steel for the student::life wing expansion, which was erected this week. This week the concrete for the Main Lobby piers was poured and the cinder block foundation was started.

July 6, 2017:
Construction Update

New Common Grounds Entrance: The steel structure for the Common Grounds entrance was completed and the steel roof deck was installed.

New Office Expansion: Wood blocking was installed around the perimeter of the roof, and installation of the exterior wall vapor barrier and wall sheeting began. Inside the new office expansion, electrical HVAC along the ceiling was started.


Office Renovations: The renovation of the old Counseling Center’s waiting room and five counseling rooms was completed on Monday. Thanks to Men’s Life ministry volunteers and Living Word staff for help during the move. To enter the Counseling Center, use door #4.


The new main corridor from Common Grounds to kid::life and the nearby renovated office spaces are almost done and should reopen in a few weeks.

The old hallway behind the Main Auditorium and adjacent offices will be renovated to include an electrical transformer, panel, and storage room; two new administrative work areas; and expanded IT and facilities offices. These rooms will be accessed from the old, but renovated adjacent open office space and are scheduled to be completed in a few weeks.

kid::life Expansions: Parents, construction continues for the new hallway that will connect the kid::life red wing to the two new large assembly rooms. This is scheduled to be completed by mid July. In the meantime, Toddlers will meet in room 317 and Ladybugs in room 314 to ensure all children are safe during construction.

Foundations for the student::life, kid::life and Main Lobby Expansions: The footings, piers, and perimeter cinder block foundations for the expansions of student::life and kid::life were completed this week. Final underground plumbing for new restrooms was completed this week.

Main Entrance Expansion: Re-bar for the piers was constructed in preparation for pouring the concrete.

June 29, 2017:
Counseling Center Almost Done!

New Common Grounds and Office Entrance: Last Friday the new Common Grounds entrance and tower were put into place. This week more of the curved entrance were put up, as well as the roof structure between the entrance and the tower. It’s almost completed.



New Office Expansion: Work this week involved installing the wood framing for the windows, running electrical conduit, and placing junction boxes. Installation of the exterior wall sheathing began and will continue into next week.

Office Renovations: The renovation of the old Counseling Center’s waiting room and five counseling rooms is almost complete. This is very exciting! The new ceiling lights and carpet were installed. After final inspection, the rooms will be turned over to the church next week. We will let you know when the Counseling Center is ready to open in its permanent location.


The old hallway behind the Main Auditorium was closed off this week. The old hall area will be renovated to include an electrical transformer, panel and storage room, two new administrative work areas, and an expanded IT office and facilities office. That renovation began last week with drywall and drop ceiling grids completed this week.

kid::life Expansion: Parents, you will see that walls were constructed for a new hallway that will connect the kid::life red wing to the two new large assembly rooms. The hallway was created by taking space from room 323 (Toddlers) and room 322 (Ladybugs). The windows in those two rooms have been covered with sheetrock. The renovations to those two classrooms are scheduled to be completed by July 7.  In the meantime, Toddlers will meet in room 317 and Ladybugs in room 314 to ensure all children are safe during construction.

Foundations for the student::life, kid::life, and Main Lobby Expansions: The footings, piers, and perimeter cinder block foundations for the expansions of student::life and kid::life were completed this week. Final underground plumbing for new restrooms was started and is due to be completed next week.

Structural steel was delivered this week and you can expect some steel columns to be erected next week.

Main Entrance Expansion: Excavations and footings were poured for the Main Lobby expansion this week.

June 15, 2017:
Construction Update

New Common Grounds and Office Entrance: The good weather we had this week helped with the progress of the construction. The most visible change you will see is the removal of the exterior portions of the Common Grounds entrance. The visible plywood wall is the temporary security wall across the Common Grounds lobby. The wall provides a security and safety barrier while structural steel is being placed for the new entrance to the expanded Common Grounds area. The steel for the roof decking of the new offices and new Common Grounds entrance has been installed.

 

 

 

 

 

Office Renovations: This week electrical wiring has been run and drywall has been installed and is almost finished and ready for paint. These are pictures of the new hallway that will connect Common Grounds with kid::life with the new layout of the office spaces left and right of the hallway. The Counseling Center counseling rooms, waiting room, and hallway have been painted and new drop ceiling framing and tiles installed. Flooring will be finished in the next few days.

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Storm Water Drains by the student::life wing: Main storm water drains from the upper side of the property and along the youth wing end of the building have been installed, which was a major effort. New sections were excavated and the drains were installed.

 

 

 

 

 

 

 

 

Foundations for the student::life Expansion: The excavation and foundations for the new meeting rooms, expanded restrooms, and sacred space were put on hold for this week to accommodate the storm water drain installation, as well as a design change needed to accommodate the plumbing of the new expanded restroom. This part of the project will continue into next week.

 

 

 

 

 

 

 

 

Foundations for kid::life Expansion: The excavation and foundation for the kid::life expansion continued this week and will run into next week.

 

June 8, 2017:
Progress & New Walls

Exciting changes are taking place inside and out! Much of the change inside has been hidden from view in safe construction zones, so this week we are bringing you photos of the office renovations.

Office renovations began on May 16 with the main office area and the Counseling Center. The doors were removed, the walls that were moving were demolished, the carpet and ceiling tiles were removed, and electrical is being reworked as needed. Last week the steel studs for the new walls to create the new hallway to connect Common Grounds with the kid::life side of the building began to emerge. New office spaces and new doorways were created. This week drywall began to be installed and new electrical wiring is being run. The Counseling Center is getting a new coat of paint as this report is being written.

Outside on the south side, new storm water runs were dug and connected to the building. Storm water runs continue to be dug and installed into next week, however, for Sunday these areas will either be plated with steel or covered with macadam.

The west wing expansion piers have been dug and some have been poured. The piers for the north canopy were framed up and were being poured Thursday afternoon as this report is being written. On Sunday you will also see additional steel framing that has been welded into place on the north office expansion.

A security wall is being built across the Common Grounds lobby. This will provide a security and safety barrier while structural steel is being placed and the existing exterior wall begins to be removed. If you are used to watching the service in the Common Grounds lobby, please join us in the Life Center.

 

 

June 2, 2017:
North-Side Progress & Shuttle Service

Now that the foundations and concrete slab have been laid you will begin to see more rapid progress on the project. This week the structural steel for the north office areas was erected and the footers for the new canopy were dug. Inside the main office area, the demolition was completed and new steel stud walls are taking shape. Outside on the south side the excavation and foundations continue and we have begun to tie the new stormwater management into the previous stormwater management on the south east corner.
Please note due to the stormwater excavation in the drive area just off the east end of the building the drive beside the building will be shut down for a period of time. Please use the adjoining parking lots as a detour around this area of excavation.
We are also highly suggesting that those with mobility challenges instead of using the drop-off area, consider parking in the handicap parking places in lot D and use the new shuttle service to the front entrance.


May 27, 2017:
South Side & Office Renovations Continue

This week exterior work was slowed by the intermittent rain which delayed concrete work. However work inside progressed on schedule and:

  • Foundations and footings for the youth expansion area were poured
  • The concrete pad for the office expansion is almost complete
  • Structural steel for the office expansion arrived and began to be placed
  • Office demolition continued removing electrical, some walls and carpet.

 We continue to find ways to improve the access to the building and your experience.  We have created an area along the fence in the drop-off zone exclusively for pedestrians. This area is coned off. We have removed all parking from the drop-off zone and are running a shuttle to/from the handicap and mobility challenged parking area in lot D just across the drive from the drop off zone. We have also expanded this parking area with additional cones reserving spots for those needing assistance.

Our desire is to serve you and make your experience arriving and departing as comfortable as possible.  While there are limitations of what we can do without complicating the construction project, we invite you to make any suggestions you feel would be helpful.

May 18, 2017:
South Side & Office Renovations Continue

This week the exterior foundations on the north side of the building were completed. A piling for the new tower is being set in place under the slab of the Common Grounds Lobby. On the south side, the footers have been dug, rebar formed, and concrete is being poured for the foundations of the expanded east wing. The Main Office and Counseling Center have been closed for renovations and interior and electrical demolition has started. As a result, if you need to travel between the east wing (Common Grounds and student::life) and the west wing (kid::life), the Main Lobby is the easiest pathway. Also, we have been providing wheelchairs at the drop-off area outside entrance 1 to assist those who need some help getting from the drop-off point to the auditorium.

A Note from Pastor Brian

Everyone has been so helpful as we make adjustments getting into and around in our building. We have many months to go, but it will be exciting every week as we see progress.

Thank you to everyone who is supporting our new building. The funds have been coming in and we are grateful for that as well.

Please keep the entire building project in your prayers: safety for workers, good weather and timely work being done, patience on the part of everyone, and that God would raise up more people who want to financially support The Best is Yet to Come campaign.

Thanks again, everyone.

In Christ,

Pastor Brian

May 11, 2017:
South Side Renovations & Hallway Blocked-Off

This week we completed vacating the main office areas, moving supplies and equipment to new locations throughout the building. On Thursday, the renovations of the main office area began. This renovation includes the creation of a new hallway from Common Grounds to the kid::life area.

For the safety of all, please do not enter the construction areas without proper authorization from the construction superintendent, whether inside the building or any of the fenced in areas outside the building.

The work on the foundations for the north office and Common Grounds entrance continues. The concrete footers were completed and the block foundations are being laid.

The work on the south side kicked into high gear this week.

* top soil was removed and stored on site

* the canopy was removed and sealed from weather

* the sidewalk was removed

* stormwater pipes that need to be re-routed were removed

* preparations for new stormwater and sewage lines began

 

 

May 9, 2017:
Foundation Work, Relocated Offices, Counseling Center

This week the foundations are continuing to be laid on the new Common Grounds entrance and staff offices by Common Grounds. The crews will continue placing rebar and pouring of the concrete foundations.

At the moment the south side of the building is seeing more destruction than construction. The canopy is being taken down and foundations are being surveyed and dug.

Our staff that worked in the Main Office have moved to other work spaces. We are so grateful for the ministry partners that have helped during this transition, thank you! The Main Office area is closed for renovations. This is where we are putting in a new hallway between Common Grounds and kid::life.

The reception area in the Main Office has now been moved to the Common Grounds Lobby. Please use door 3 as the new Main Office door where you can connect with our receptionist Amy if you have an appointment at the church.

Our Counseling Center has moved to the student::life wing. The waiting area at the opposite end of the hallway can be accessed via door 2.

May 2, 2017:
Foundation Work & Entrance Update

The next step in the site preparation is happening this week and you will notice several changes: 1) foundation work has begun for the new offices; 2) a construction fence has been installed around the south side of the building and around much of the lower parking lot; 3) all but one entrance to the Main Lobby has been closed; and 4) the main office staff has been moved to other locations.

Change is often difficult to deal with and these changes will cause challenges – disrupted routines, people not being where they used to be, and perhaps having to walk a little farther. We pray that everyone will have patience and extend grace as we move into the time where we ask God to “bless this mess.”

April 26, 2017:
Office Construction Begins

As you drive into the north parking lot this week (Common Grounds entrance), you will notice that the heavy equipment that was here last Sunday hasn’t been sitting idle. A portion of the parking lot and sidewalk near the previous entrance has been removed in preparation for the office expansion. You are now able to see the “footprint” of the new entrance and extended offices. This new space will allow all the staff to be in the same location. It will also allow easier access to the kid:life wing from Common Grounds.

The preparation for the foundation for the new office expansion will begin and should take a week and a half to complete.

April 22, 2017:
Parking & Entrance Information

It is exciting to see the construction beginning to take place! Because more than half of our building exterior is being expanded, the number of entrances is being reduced during the construction period.

New entrances and closest doorways to the following areas:

Entrance 1: Main Lobby
Entrance 2: student::life
Entrance 3: Common Grounds, Church Office, and receptionist                                    Entrances 4 & 5: kid::life and the Counseling Center

Please use parking lots farther away. IF you are able-bodied and can walk a few extra yards, help us honor our guests, the elderly, and those with physical challenges by passing up the parking spots closest to the doors and leaving them for others.

Thank you for your patience during this temporary inconvenience for permanent improvement.

April 14, 2017:
Property Map &  Entrance Information

The Best Is Yet to Come is finally becoming a reality as we begin the building expansion. This page will be used to provide updates about the construction. We are praying that the work is completed by the end of the year.

Our contractor, Wohlson Construction, will be preparing the site to begin work following Easter Sunday. Our primary concern is for safe access to the building and that the construction will be done in a timely manner. A safety and security fence will be installed around the construction areas, which will limit access to some areas. We have worked closely with the contractor to develop a plan that will be the least disruptive to our regular ministry.

This preparation will likely change the way you enter the building. A number of current parking spots will be covered by the construction, so you also may need to park in a different location. We have numbered the entry doors from 1 to 5. Each entry door will have a large number above the door to identify that entrance. Here is a chart to help you know which door to enter for each part of the building and the best place to park for that entrance. There is a map included to help you visualize the building and parking lots.

Door #1: Lobby and Main Auditorium entrance. There will be a drop-off point near this entrance with a few handicapped spaces in parking lot A and more in lot D. Other parking will be available in lots B, C, and D.

Door #2: student::life area on the south side of the building. The best parking for this entrance will be in lots D and E.

Door #3: New entrance for Common Grounds and the office reception area. Located off the patio area, the best parking for this entrance will be in lots D, E, and F. There will be handicapped parking in lot F near the building.

Doors #4 and #5: kid::life entryways. These entrances are in the same location they were previously–on the northwest side of the building. Parking spaces in lots F, G, and H are closest to these entrances.

To make sure that our guests and first-time visitors have a great experience, we request that able-bodied staff and ministry partners park in lots D and E at the ends farthest from the building.

Thank you for working with us during the expansion. If you have any questions, please do not hesitate to contact John Hillard.

April 13, 2017:
New Common Ground Door Being Installed

The initial step in the construction process is to create a new entrance into Common Grounds. On Wednesday, April 12 our construction company started converting a window into a set of doors. This entrance is being designed to create a greater connectivity between Common Grounds and the patio, but also serves as an alternate entrance when the current Common Grounds entrance is closed next week for the beginning of the expansion.

On Sunday, you will see clear, thick draping in Common Grounds to prevent any dust or debris from coming into the building.

Phase1_Expansion